ORE TOLLING AND CONCENTRATE PURCHASE AGREEMENT PROGRESS UPDATE

Page 1 of 1
  1. 82.9k
    Posts

    Drafting of pivotal Offtake Agreement with BHP Nickel West advancing positively with
    completion expected before 18 July 2019
    Further to its ASX announcement of 19 March 2019, Mincor Resources NL (ASX: MCR, “Mincor” or the “Company”)
    advises that it is progressing drafting with BHP Billiton Nickel West Pty Ltd (“BHP Nickel West”) on the details of a
    binding Ore Tolling and Concentrate Purchase Agreement (“Offtake Agreement”) for its Kambalda nickel business.
    The term sheet signed with BHP Nickel West in March 2019 set out the major operating principles that will form
    the basis for the Offtake Agreement. The term sheet was subject to the completion of a full form Offtake Agreement
    within two months (which could be extended by mutual agreement).
    While discussions regarding the full-form Offtake Agreement have made good progress, the parties have agreed to
    extend the completion date to 18 July 2019 to provide additional time to finalise.
    The key commercial terms of the new agreement, which will replace the historical 20-year agreement Mincor had
    with BHP Nickel West, were set out in the Company’s ASX release of 19 March 2019.
    Mincor’s Managing Director, Mr David Southam, said: “We set an ambitious timeline when we signed the term
    sheet in March and, while our teams have been working very well together and have made good progress, more
    time is needed to allow us to deal adequately with all aspects of this comprehensive agreement.
    “We are looking forward to finalising the agreement, building upon the foundations laid out in the term sheet for
    a commercially attractive processing and offtake solution for our Kambalda nickel sulphide business that will
    underpin our plans to fast-track the restart of nickel mining.”

    courtesy of Bell Direct
    ===========================================================================

    ( DYOR )

    i hold MCR

    tread carefully here , production costs will be hard to predict ( you can't count on a windfall pocket of cobalt again to boost the balance sheet )

  2. 82.9k
    Posts

    FIRST PAYMENT FOR NICKEL CONCENTRATE RECEIVED AS MINCOR DELIVERS
    PRODUCTION RESTART ON TIME AND BELOW PEAK FUNDING GUIDANCE
    Receipt of first cash-flow results in another milestone delivered by Mincor
    • Mincor receives net proceeds of A$25.3 million from BHP Nickel West, representing 90% of the payment
    for nickel concentrate calculated for ore deliveries up to 31 May 2022. Final 10% payment due in August.
    • The net proceeds figure is derived from 1,003 tonnes of nickel in concentrate and includes deductions for
    processing charges and freight rates consistent with the OTCPA with BHP Nickel West.
    • Mincor has successfully delivered the project for an actual peak funding outlay of A$98 million, ~8% below
    the previous estimate of A$107 million (see ASX announcement 7 September 2021). Peak funding
    represents capital expenditure and working capital costs prior to first sales.
    • This outcome represents an outstanding result for Mincor, with the successful delivery of two mining
    operations developed entirely during the COVID-19 pandemic period.
    • Major capital works now predominantly complete, with the new Cassini Village the final outstanding
    project scheduled for completion early in the December 2022 quarter, and slightly lower than budget.
    Mincor Resources NL (ASX: MCR, “Mincor” or the “Company”) is pleased to advise that it has received payment
    for the Company’s first parcel of nickel ore to be processed through BHP’s Kambalda Nickel Concentrator.
    The payment of A$25.3 million represents sales receipts for 90% of the imputed nickel concentrate production
    up to 31 May 2022 (less processing and freight charges) with the balance to be paid in August, under the terms
    of the enhanced Ore Tolling and Concentrate Purchase Agreement (OTCPA – see ASX announcement, 29 April
    2022) with BHP Nickel West.
    Sales for the month of May have been derived from the steady build-up of development ore stockpiles over a
    number of months. Mincor continues to be laser focused on its ramp-up activities at both mining centres, with
    a key operational milestone achieved last week with the first stope opened up at the Northern Operations.
    Importantly, with the receipt of this first tranche of sales revenue, Mincor has delivered the restart of its
    Kambalda Nickel Operations for an actual peak funding outlay of A$98 million, being ~8% below the previously
    disclosed figure of A$107 million.
    This is an outstanding achievement given that project development has been executed while Mincor has been
    dealing with the challenges of the global COVID-19 pandemic and its flow-on impacts which have been widely
    reported.
    Major capital works are now predominantly complete, with the Cassini accommodation village expected to be
    completed early in the December 2022 quarter. At this stage, the total cost of the Village is estimated to be
    marginally lower than the A$15 million guidance (see ASX announcement 7 September 2021) with all long-lead
    and major items under firm order with deposits paid.
    At the same time, the Company is looking forward to delivering an Initial Mineral Resource for the newly
    identified LN04a surface at the Golden Mile (Northern Operations) in July, underpinned by the first stage of
    results delivered so far ahead of what is expected to be a significant ongoing drilling program for FY23.
    2
    Management Comment
    Mincor’s Managing Director, David Southam, said: “Receipt of first nickel sales is yet another outstanding
    achievement for the Company as we complete our return to the global ranks of nickel producers.
    “We are also particularly pleased that we have achieved this milestone, including the development of two
    underground mines, below our peak funding estimate. This is a tremendous result in one of the most challenging
    operational environments in recent memory, and is testament to the dedication and efforts of our people and
    our contracting and operating partners, such as BHP – all of whom have been aligned to the successful
    resumption of high-quality nickel production in Western Australia.
    “We are continuing to invest strongly in exploration, with the first tangible payback from our drilling success at
    the Golden Mile due to be delivered in July with an initial Mineral Resource for the LN04a. The program for further
    drilling and extensional work will continue in FY23 with a focus on the Golden Mile and drilling from favourable
    underground positions at Cassini to target extensions of the Cassini Main orebody and the adjacent Cassini North
    channel.”
    Approved by:
    Board of Mincor Resources NL

    courtesy of Bell Direct
    ===========================================================================

    ( DYOR )

    i hold MCR ( 'free-carried ' )

Your browser is too old for TopStocks and not secure. Please update your browser